REVISIONS | 6/25/2020 | Deena Berens |
(6/25/2020 12:11 PM DB1)
REV 1 READY TO ISSUE in approvd bin. FEES DUE. emailed applicant to make appt. (FOLDED)
(6/29/2020 2:20 PM LL3)
REV 1 ISSUED TO ALEX (folded)
(7/14/2020 3:30 PM DB1)
Rev. 2 approved and placed in plans ready for issuance bin (rolled). Emailed applicant to make an appt.
(7/15/2020 9:23 AM DB1)
Ron Bartlo has a change to the revision. Per C Yado, he should submit the change prior to us releasing elec rev 2.
(7/29/2020 11:35 AM LL3)
APPLICANT TO SUBMIT 3 NEW REV 2 SETS FOR REVIEW. PLANNING REQUIRED CORRECTIONS THAT ADDED NEW SHEETS SO REV 2 PLANS SUBMITTED ON 7/21 HAVE BEEN RECYCLED.
(8/21/2020 11:43 AM DB1)
EMAILED RON TO MAKE APPT TO PICK UP REVISION AND THE FEE INVOICE. PLANS IN APPROVED AREA. ROLLED.
(11/19/2020 8:53 AM RS1)
REV-3 READY TO PICK UP, APPLICANT NOTIFIED VIA EMAIL - ROB
(1/25/2021 12:04 PM DB1)
rev 4 in back approved area folded. pending fees.
(1/25/2021 12:04 PM DB1)
emailed Rev invoice. fees paid |
More Info
|
RE-STAMP | 6/22/2020 | Deena Berens |
(6/22/2020 10:54 AM DB1)
sent to planning. left on lauras desk. |
More Info
|
PERMIT READY TO ISSUE | 4/28/2020 | Rob Stauffacher |
(4/23/2020 12:41 PM RS1)
OWNER APPROVAL REQUIRED, FEES DUE, CONTRACTOR REQUIRED, ADA FORM, SDG&E WORK ORDER REQUIRED, PLANS TO APPROVED BIN, APPLICANT PREVIOUSLY NOTIFIED BY DEENA RE:SDGE WORKORDER - ROB
(4/28/2020 9:03 AM DB1)
CARLOS ALLOWS DEFERMENT OF SDGE WORKORDER :( . OK TO ISSUE PERMIT |
More Info
|
MISC/COMMENTS | 4/9/2020 | Deena Berens |
(4/9/2020 3:44 PM DB1)
plasn left at planning counter for restamping.
emailed applicant requested SDGE workorder, contractors info and C & D form.
(4/20/2020 11:38 AM DB1)
sent a will serve letter and C D Forms for 73%
(4/28/2020 9:56 AM DB1)
requested POCKET CARD, WORKERS COMP, LETTER OF AUTHORIZATIONS AND BL
(4/30/2020 1:41 PM DB1)
all doc received. wait on BL
(4/30/2020 1:46 PM DB1)
SENT FEE INVOICE
(4/30/2020 3:07 PM DB1)
BL obtained. Sent permit for signature
(5/1/2020 4:02 PM DB1)
INSPECTOR STEVE INFORMS THEY HAD STARTED WORK WWITHOUT PERMIMT AND HAD TORN UP ROOFING AND STARTED COVERING UP SHEATHING. THE ORIGINAL APPLICATION DID NOT INCLUDE ROOFING , BUT THE PLAN NOTED ROOFING REPLACEMENT. THE ORIGNAL VALUATION ON APPLICATION WAS 30k AND DID NOT INCLUDED ROOFING PORTION. CONTRACTOR PAID A PORTION OF THE FEES, BUT I ADDED ADDITIONAL FEES FOR ROOFING AND CE FEES FOR STARTING WITHOUT BENEFIT OF PERMIT. AND ADDITIONAL C D BOND AMOUNT.
EMAILED APPLICANT/CONTRACTOR AND INCLUDED PLANNING, PERMIT TECHS AND INSPECTOR. INSPECTOR NEEDS TO DISCUSS WITH PLANNING ON MONDAY AND AFTER APPROVED THEY NEED TO PAY FEES, THEN SIGN THE PERMIT FOR ISSUANCE.
(5/4/2020 2:43 PM DB1)
General will not be included roofing on this permit. roofing cointractor sent in application for own work.
(5/4/2020 2:53 PM DB1)
revised Valuation from 30k to 153k- requested additional permit fees
(5/5/2020 9:25 AM DB1)
ROOFING CONTRACT TO BE ADDED TO THIS PERMIT.
(5/5/2020 10:05 AM DB1)
sent revised fee invoice to applicant.
(5/5/2020 10:16 AM DB1)
additional fees paid. will send revised permit for signature
(5/5/2020 10:45 AM DB1)
PERMIT SIGNED. PERMIT PACKAGE LEFT AT FRONT DOOR FOR PICK UP. |